FAR Part 36 is primarily concerned with which type of contracts?

Study for the Federal Acquisition Regulation (FAR) Test. Prepare with comprehensive flashcards and multiple-choice questions, each equipped with detailed hints and explanations. Master your exam!

FAR Part 36 specifically addresses the procurement of construction and architect-engineering contracts. This part of the Federal Acquisition Regulation establishes guidelines for contracting procedures, requirements, and policies that are unique to these types of projects. The focus on construction and architect-engineering contracts includes not only the acquisition of construction services but also the selection of architects and engineers for project design and related services, which are critical in ensuring the successful execution of construction projects.

Understanding FAR Part 36's focus on these contracts helps in recognizing the importance of regulations that govern aspects such as contract types, methods of procurement, and the criteria for selecting contractors and consultants. The provisions outlined in this part aim to ensure compliance with legal requirements while promoting fairness and competition in the procurement process for construction projects.

Other choices encompass areas covered in different parts of the FAR; for instance, service contracting is discussed in FAR Part 37, while research and development contracting typically falls under FAR Part 35. Federal Supply Schedule contracting has its own set of regulations laid out in FAR Part 38. Therefore, choosing construction and architect-engineering contracts as the primary focus of FAR Part 36 aligns perfectly with the established guidelines and objectives of this specific part.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy