Which FAR part is responsible for addressing Federal Supply Schedule contracting?

Study for the Federal Acquisition Regulation (FAR) Test. Prepare with comprehensive flashcards and multiple-choice questions, each equipped with detailed hints and explanations. Master your exam!

The correct answer is based on the specific focus of FAR Part 38, which deals with Federal Supply Schedule (FSS) contracting. FAR Part 38 provides the policies and procedures that govern the acquisition of commercial items and services through these schedules, which are established by the General Services Administration (GSA). This part outlines the framework under which federal agencies can procure goods and services efficiently and economically by leveraging pre-negotiated contracts.

The significance of Federal Supply Schedules lies in their ability to streamline the procurement process, enabling agencies to obtain commonly used items and services quickly and at favorable prices. This is essential for maintaining the efficiency and effectiveness of federal procurement operations.

Each of the other parts mentioned in the question has a different focus. Part 36 pertains to construction and architect-engineer services, Part 35 addresses research and development contracting, and Part 31 focuses on contract cost principles and procedures. Therefore, they do not cover the scope of Federal Supply Schedule contracting, which is specifically and thoroughly addressed in FAR Part 38.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy